Core Infrastructure Refresh - Package 1 & 3 (Peter MAC) appears in 8 snapshots of the Victorian IT dashboard, from 2022-23 Q3 to 2024-25 Q2.
Its cost is $1.2m at 2024-25 Q2, against $1.3m at its baseline: -3%.
Its latest rating is Green (2024-25 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Core Infrastructure Refresh - Package 1 & 3. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/petermaccoreinfrastructurerefreshpackage13, as at 18 May 2026. Licence: CC BY 4.0.
How much does Core Infrastructure Refresh - Package 1 & 3 cost? Its cost is $1.2m at 2024-25 Q2, against $1.3m at its baseline: -3%.
What is Core Infrastructure Refresh - Package 1 & 3's latest rating? Its latest rating is Green (2024-25 Q2).