Peninsula Health Project Phoenix (MePACS Refresh) (PEN Health) appears in 6 snapshots of the Victorian IT dashboard, from 2024-25 Q1 to 2025-26 Q2.
Its cost is $2.6m at 2025-26 Q2, against $2.6m at its baseline: +0%.
Its planned finish is 30 Jun 2026, 8 months later than the 31 Oct 2025 first planned.
Its latest rating is Green (2025-26 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Peninsula Health Project Phoenix (MePACS Refresh). Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/penhealthpeninsulahealthprojectphoenixmepacsrefresh, as at 18 May 2026. Licence: CC BY 4.0.
How much does Peninsula Health Project Phoenix (MePACS Refresh) cost? Its cost is $2.6m at 2025-26 Q2, against $2.6m at its baseline: +0%.
Is Peninsula Health Project Phoenix (MePACS Refresh) late? Its planned finish is 30 Jun 2026, 8 months later than the 31 Oct 2025 first planned.
What is Peninsula Health Project Phoenix (MePACS Refresh)'s latest rating? Its latest rating is Green (2025-26 Q2).