Peninsula Health Project Lotus (People Hub) (PEN Health) appears in 4 snapshots of the Victorian IT dashboard, from 2023-24 Q3 to 2024-25 Q2.
Its planned finish is 20 Dec 2024, 1 months earlier than the 31 Jan 2025 first planned.
Its latest rating is Green (2024-25 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Peninsula Health Project Lotus (People Hub). Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/penhealthpeninsulahealthprojectlotuspeoplehub, as at 18 May 2026. Licence: CC BY 4.0.
Is Peninsula Health Project Lotus (People Hub) late? Its planned finish is 20 Dec 2024, 1 months earlier than the 31 Jan 2025 first planned.
What is Peninsula Health Project Lotus (People Hub)'s latest rating? Its latest rating is Green (2024-25 Q2).