Q05765 - SCADA Mosaic Upgrade (MW) appears in 2 snapshots of the Victorian IT dashboard, from 2016-17 Q4 to 2017-18 Q1.
Its cost is $0.7m at 2017-18 Q1, against $1.1m at its baseline: -32%.
Its planned finish is 2 Nov 2017, 1 months earlier than the 30 Nov 2017 first planned.
Its latest rating is Green (2017-18 Q1).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Q05765 - SCADA Mosaic Upgrade. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/mwq05765scadamosaicupgrade, as at 18 May 2026. Licence: CC BY 4.0.
How much does Q05765 - SCADA Mosaic Upgrade cost? Its cost is $0.7m at 2017-18 Q1, against $1.1m at its baseline: -32%.
Is Q05765 - SCADA Mosaic Upgrade late? Its planned finish is 2 Nov 2017, 1 months earlier than the 30 Nov 2017 first planned.
What is Q05765 - SCADA Mosaic Upgrade's latest rating? Its latest rating is Green (2017-18 Q1).