Q05582 - Improvements to Portfolio, Program and Project Management (MW) appears in one Victorian IT dashboard snapshot, 2017-18 Q1.
Its cost is $2.4m at 2017-18 Q1, against $2.5m at its baseline: -3%.
Its planned finish is 28 Mar 2018, 1 months later than the 28 Feb 2018 first planned.
Its latest rating is Green (2017-18 Q1).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Q05582 - Improvements to Portfolio, Program and Project Management. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/mwq05582improvementstoportfolioprogramandprojectmanagement, as at 18 May 2026. Licence: CC BY 4.0.
How much does Q05582 - Improvements to Portfolio, Program and Project Management cost? Its cost is $2.4m at 2017-18 Q1, against $2.5m at its baseline: -3%.
Is Q05582 - Improvements to Portfolio, Program and Project Management late? Its planned finish is 28 Mar 2018, 1 months later than the 28 Feb 2018 first planned.
What is Q05582 - Improvements to Portfolio, Program and Project Management's latest rating? Its latest rating is Green (2017-18 Q1).