Project Controls Solution (MTIA) appears in 7 snapshots of the Victorian IT dashboard, from 2019-20 Q4 to 2021-22 Q2.
Its cost is $3.0m at 2021-22 Q2, against $4.1m at its baseline: -26%.
Its planned finish is 25 Nov 2021, 6 months later than the 4 Jun 2021 first planned.
Its latest rating is Green (2021-22 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Project Controls Solution. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/mtiaprojectcontrolssolution, as at 18 May 2026. Licence: CC BY 4.0.
How much does Project Controls Solution cost? Its cost is $3.0m at 2021-22 Q2, against $4.1m at its baseline: -26%.
Is Project Controls Solution late? Its planned finish is 25 Nov 2021, 6 months later than the 4 Jun 2021 first planned.
What is Project Controls Solution's latest rating? Its latest rating is Green (2021-22 Q2).