Mobile Data for Vehicles Pilot (MFESB) appears in 11 snapshots of the Victorian IT dashboard, from 2017-18 Q2 to 2019-20 Q4.
Its cost is $2.8m at 2019-20 Q4, against $1.8m at its baseline: +60%.
Its planned finish is 30 Jun 2020, 36 months later than the 30 Jun 2017 first planned.
Its latest rating is Green (2019-20 Q4), up from Amber at 2017-18 Q2.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Mobile Data for Vehicles Pilot. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/mfesbmobiledataforvehiclespilot, as at 18 May 2026. Licence: CC BY 4.0.
How much does Mobile Data for Vehicles Pilot cost? Its cost is $2.8m at 2019-20 Q4, against $1.8m at its baseline: +60%.
Is Mobile Data for Vehicles Pilot late? Its planned finish is 30 Jun 2020, 36 months later than the 30 Jun 2017 first planned.
What is Mobile Data for Vehicles Pilot's latest rating? Its latest rating is Green (2019-20 Q4), up from Amber at 2017-18 Q2.