Work my way (MELB Water) appears in 3 snapshots of the Victorian IT dashboard, from 2019-20 Q1 to 2019-20 Q3.
Its cost is $1.9m at 2019-20 Q3, against $2.2m at its baseline: -11%.
Its latest rating is Red (2019-20 Q3).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Work my way. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/melbwaterworkmyway, as at 18 May 2026. Licence: CC BY 4.0.
How much does Work my way cost? Its cost is $1.9m at 2019-20 Q3, against $2.2m at its baseline: -11%.
What is Work my way's latest rating? Its latest rating is Red (2019-20 Q3).