Website New Services (MELB Water) appears in 11 snapshots of the Victorian IT dashboard, from 2021-22 Q1 to 2023-24 Q3.
Its planned finish is 1 Mar 2024, 20 months later than the 30 Jun 2022 first planned.
Its latest rating is Green (2023-24 Q3).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Website New Services. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/melbwaterwebsitenewservices, as at 18 May 2026. Licence: CC BY 4.0.
Is Website New Services late? Its planned finish is 1 Mar 2024, 20 months later than the 30 Jun 2022 first planned.
What is Website New Services's latest rating? Its latest rating is Green (2023-24 Q3).