Q05765 - SCADA Mosaic Upgrade (MELB Water) appears in one Victorian IT dashboard snapshot, 2017-18 Q2.
Its cost is $1.1m at 2017-18 Q2, against $1.1m at its baseline: no change.
Its planned finish is 2 Nov 2017, 1 months earlier than the 30 Nov 2017 first planned.
Its latest rating is Green (2017-18 Q2).
The source marks it completed.