Q05754 - Site Security Upgrade Project (Phase 2) (MELB Water) appears in 5 snapshots of the Victorian IT dashboard, from 2017-18 Q2 to 2018-19 Q2.
Its cost is $1.9m at 2018-19 Q2, against $1.6m at its baseline: +18%.
Its planned finish is 30 Sep 2018, 8 months later than the 12 Feb 2018 first planned.
Its latest rating is Green (2018-19 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Q05754 - Site Security Upgrade Project (Phase 2). Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/melbwaterq05754sitesecurityupgradeprojectphase2, as at 18 May 2026. Licence: CC BY 4.0.
How much does Q05754 - Site Security Upgrade Project (Phase 2) cost? Its cost is $1.9m at 2018-19 Q2, against $1.6m at its baseline: +18%.
Is Q05754 - Site Security Upgrade Project (Phase 2) late? Its planned finish is 30 Sep 2018, 8 months later than the 12 Feb 2018 first planned.
What is Q05754 - Site Security Upgrade Project (Phase 2)'s latest rating? Its latest rating is Green (2018-19 Q2).