Q05582 - Improvements to Portfolio, Program and Project Management (MELB Water) appears in 3 snapshots of the Victorian IT dashboard, from 2017-18 Q2 to 2017-18 Q4.
Its cost is $2.5m at 2017-18 Q4, against $2.5m at its baseline: no change.
Its planned finish is 28 Mar 2018, 1 months later than the 28 Feb 2018 first planned.
Its latest rating is Green (2017-18 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Q05582 - Improvements to Portfolio, Program and Project Management. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/melbwaterq05582improvementstoportfolioprogramandprojectmanagement, as at 18 May 2026. Licence: CC BY 4.0.
How much does Q05582 - Improvements to Portfolio, Program and Project Management cost? Its cost is $2.5m at 2017-18 Q4, against $2.5m at its baseline: no change.
Is Q05582 - Improvements to Portfolio, Program and Project Management late? Its planned finish is 28 Mar 2018, 1 months later than the 28 Feb 2018 first planned.
What is Q05582 - Improvements to Portfolio, Program and Project Management's latest rating? Its latest rating is Green (2017-18 Q4).