Operational Data Store Upgrade (MELB Water) appears in 7 snapshots of the Victorian IT dashboard, from 2019-20 Q3 to 2021-22 Q1.
Its planned finish is 15 Jul 2021, 4 months later than the 2 Mar 2021 first planned.
Its latest rating is Green (2021-22 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Operational Data Store Upgrade. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/melbwateroperationaldatastoreupgrade, as at 18 May 2026. Licence: CC BY 4.0.
Is Operational Data Store Upgrade late? Its planned finish is 15 Jul 2021, 4 months later than the 2 Mar 2021 first planned.
What is Operational Data Store Upgrade's latest rating? Its latest rating is Green (2021-22 Q1).