Network Hardware Refresh 22/23 (MELB Water) appears in 9 snapshots of the Victorian IT dashboard, from 2022-23 Q3 to 2024-25 Q3.
Its cost is $3.9m at 2024-25 Q3, against $3.2m at its baseline: +22%.
Its planned finish is 14 Mar 2025, 11 months later than the 4 Apr 2024 first planned.
Its latest rating is Green (2024-25 Q3).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Network Hardware Refresh 22/23. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/melbwaternetworkhardwarerefresh2223, as at 18 May 2026. Licence: CC BY 4.0.
How much does Network Hardware Refresh 22/23 cost? Its cost is $3.9m at 2024-25 Q3, against $3.2m at its baseline: +22%.
Is Network Hardware Refresh 22/23 late? Its planned finish is 14 Mar 2025, 11 months later than the 4 Apr 2024 first planned.
What is Network Hardware Refresh 22/23's latest rating? Its latest rating is Green (2024-25 Q3).