Network Hardware Refresh 21/22 (MELB Water) appears in 6 snapshots of the Victorian IT dashboard, from 2021-22 Q2 to 2022-23 Q3.
Its cost is $2.4m at 2022-23 Q3, against $2.0m at its baseline: +20%.
Its planned finish is 29 Mar 2023, 5 months later than the 31 Oct 2022 first planned.
Its latest rating is Green (2022-23 Q3).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Network Hardware Refresh 21/22. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/melbwaternetworkhardwarerefresh2122, as at 18 May 2026. Licence: CC BY 4.0.
How much does Network Hardware Refresh 21/22 cost? Its cost is $2.4m at 2022-23 Q3, against $2.0m at its baseline: +20%.
Is Network Hardware Refresh 21/22 late? Its planned finish is 29 Mar 2023, 5 months later than the 31 Oct 2022 first planned.
What is Network Hardware Refresh 21/22's latest rating? Its latest rating is Green (2022-23 Q3).