Network Architecture Improvements SDWAN (MELB Water) appears in 13 snapshots of the Victorian IT dashboard, from 2022-23 Q2 to 2025-26 Q2.
Its cost is $3.5m at 2025-26 Q2, against $1.2m at its baseline: +192%.
Its planned finish is 9 Dec 2026, 38 months later than the 10 Oct 2023 first planned.
Its latest rating is Green (2025-26 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Network Architecture Improvements SDWAN. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/melbwaternetworkarchitectureimprovementssdwan, as at 18 May 2026. Licence: CC BY 4.0.
How much does Network Architecture Improvements SDWAN cost? Its cost is $3.5m at 2025-26 Q2, against $1.2m at its baseline: +192%.
Is Network Architecture Improvements SDWAN late? Its planned finish is 9 Dec 2026, 38 months later than the 10 Oct 2023 first planned.
What is Network Architecture Improvements SDWAN's latest rating? Its latest rating is Green (2025-26 Q2).