HR Modernisation (MELB Water) appears in 13 snapshots of the Victorian IT dashboard, from 2022-23 Q2 to 2025-26 Q2.
Its cost is $6.9m at 2025-26 Q2, against $2.7m at its baseline: +153%.
Its planned finish is 15 Aug 2025, 9 months later than the 19 Nov 2024 first planned.
Its latest rating is Green (2025-26 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: HR Modernisation. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/melbwaterhrmodernisation, as at 18 May 2026. Licence: CC BY 4.0.
How much does HR Modernisation cost? Its cost is $6.9m at 2025-26 Q2, against $2.7m at its baseline: +153%.
Is HR Modernisation late? Its planned finish is 15 Aug 2025, 9 months later than the 19 Nov 2024 first planned.
What is HR Modernisation's latest rating? Its latest rating is Green (2025-26 Q2).