Finance System Cloud Transition (MELB Water) appears in 9 snapshots of the Victorian IT dashboard, from 2023-24 Q1 to 2025-26 Q1.
Its cost is $3.3m at 2025-26 Q1, against $1.8m at its baseline: +81%.
Its planned finish is 15 Sep 2025, 9 months later than the 17 Dec 2024 first planned.
Its latest rating is Green (2025-26 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Finance System Cloud Transition. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/melbwaterfinancesystemcloudtransition, as at 18 May 2026. Licence: CC BY 4.0.
How much does Finance System Cloud Transition cost? Its cost is $3.3m at 2025-26 Q1, against $1.8m at its baseline: +81%.
Is Finance System Cloud Transition late? Its planned finish is 15 Sep 2025, 9 months later than the 17 Dec 2024 first planned.
What is Finance System Cloud Transition's latest rating? Its latest rating is Green (2025-26 Q1).