Enablement of Information Governance in repositories (MELB Water) appears in 7 snapshots of the Victorian IT dashboard, from 2021-22 Q1 to 2022-23 Q3.
Its planned finish is 2 Mar 2023, 5 months later than the 28 Sep 2022 first planned.
Its latest rating is Green (2022-23 Q3).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Enablement of Information Governance in repositories. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/melbwaterenablementofinformationgovernanceinrepositories, as at 18 May 2026. Licence: CC BY 4.0.
Is Enablement of Information Governance in repositories late? Its planned finish is 2 Mar 2023, 5 months later than the 28 Sep 2022 first planned.
What is Enablement of Information Governance in repositories's latest rating? Its latest rating is Green (2022-23 Q3).