Cisco Telephony Migration (MELB Water) appears in 6 snapshots of the Victorian IT dashboard, from 2019-20 Q3 to 2020-21 Q4.
Its cost is $1.1m at 2020-21 Q4, against $1.1m at its baseline: +5%.
Its planned finish is 30 Jun 2021, 2 months later than the 26 Apr 2021 first planned.
Its latest rating is Green (2020-21 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Cisco Telephony Migration. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/melbwaterciscotelephonymigration, as at 18 May 2026. Licence: CC BY 4.0.
How much does Cisco Telephony Migration cost? Its cost is $1.1m at 2020-21 Q4, against $1.1m at its baseline: +5%.
Is Cisco Telephony Migration late? Its planned finish is 30 Jun 2021, 2 months later than the 26 Apr 2021 first planned.
What is Cisco Telephony Migration's latest rating? Its latest rating is Green (2020-21 Q4).