Audio Visual Remediation (MELB Water) appears in 18 snapshots of the Victorian IT dashboard, from 2021-22 Q1 to 2025-26 Q2.
Its cost is $1.2m at 2025-26 Q2, against $2.4m at its baseline: -49%.
Its planned finish is 5 Nov 2025, 34 months later than the 10 Jan 2023 first planned.
Its latest rating is Amber (2025-26 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Audio Visual Remediation. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/melbwateraudiovisualremediation, as at 18 May 2026. Licence: CC BY 4.0.
How much does Audio Visual Remediation cost? Its cost is $1.2m at 2025-26 Q2, against $2.4m at its baseline: -49%.
Is Audio Visual Remediation late? Its planned finish is 5 Nov 2025, 34 months later than the 10 Jan 2023 first planned.
What is Audio Visual Remediation's latest rating? Its latest rating is Amber (2025-26 Q2).