Asset management system upgrade (MELB Water) appears in 6 snapshots of the Victorian IT dashboard, from 2017-18 Q3 to 2018-19 Q4.
Its cost is $1.6m at 2018-19 Q4, against $2.1m at its baseline: -23%.
Its planned finish is 14 May 2019, 2 months later than the 5 Mar 2019 first planned.
Its latest rating is Green (2018-19 Q4).
The source marks it completed.