Asset management procurement (MELB Water) appears in 5 snapshots of the Victorian IT dashboard, from 2018-19 Q4 to 2019-20 Q4.
Its cost is $1.9m at 2019-20 Q4, against $1.9m at its baseline: +2%.
Its planned finish is 18 May 2020, 2 months later than the 30 Mar 2020 first planned.
Its latest rating is Green (2019-20 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Asset management procurement. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/melbwaterassetmanagementprocurement, as at 18 May 2026. Licence: CC BY 4.0.
How much does Asset management procurement cost? Its cost is $1.9m at 2019-20 Q4, against $1.9m at its baseline: +2%.
Is Asset management procurement late? Its planned finish is 18 May 2020, 2 months later than the 30 Mar 2020 first planned.
What is Asset management procurement's latest rating? Its latest rating is Green (2019-20 Q4).