Network Modernisation (WAN) (MelbPoly) appears in 4 snapshots of the Victorian IT dashboard, from 2017-18 Q2 to 2018-19 Q1.
Its planned finish is 31 Aug 2018, 3 months later than the 31 May 2018 first planned.
Its latest rating is Green (2018-19 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Network Modernisation (WAN). Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/melbpolynetworkmodernisationwan, as at 18 May 2026. Licence: CC BY 4.0.
Is Network Modernisation (WAN) late? Its planned finish is 31 Aug 2018, 3 months later than the 31 May 2018 first planned.
What is Network Modernisation (WAN)'s latest rating? Its latest rating is Green (2018-19 Q1).