CMI Data Access Project (Melb H) appears in 10 snapshots of the Victorian IT dashboard, from 2023-24 Q1 to 2025-26 Q2.
Its cost is $1.2m at 2025-26 Q2, against $1.1m at its baseline: +6%.
Its planned finish is 28 Nov 2025, 17 months later than the 30 Jun 2024 first planned.
Its latest rating is Green (2025-26 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: CMI Data Access Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/melbhcmidataaccessproject, as at 18 May 2026. Licence: CC BY 4.0.
How much does CMI Data Access Project cost? Its cost is $1.2m at 2025-26 Q2, against $1.1m at its baseline: +6%.
Is CMI Data Access Project late? Its planned finish is 28 Nov 2025, 17 months later than the 30 Jun 2024 first planned.
What is CMI Data Access Project's latest rating? Its latest rating is Green (2025-26 Q2).