Business Transformation Program - Horizon 1 (LMUR Water) appears in 9 snapshots of the Victorian IT dashboard, from 2021-22 Q1 to 2023-24 Q1.
Its cost is $6.2m at 2023-24 Q1, against $5.2m at its baseline: +19%.
Its planned finish is 31 Aug 2023, 2 months later than the 30 Jun 2023 first planned.
Its latest rating is Green (2023-24 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Business Transformation Program - Horizon 1. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/lmurwaterbusinesstransformationprogramhorizon1, as at 18 May 2026. Licence: CC BY 4.0.
How much does Business Transformation Program - Horizon 1 cost? Its cost is $6.2m at 2023-24 Q1, against $5.2m at its baseline: +19%.
Is Business Transformation Program - Horizon 1 late? Its planned finish is 31 Aug 2023, 2 months later than the 30 Jun 2023 first planned.
What is Business Transformation Program - Horizon 1's latest rating? Its latest rating is Green (2023-24 Q1).