Unified Communications Infrastructure (LMRHA) appears in 8 snapshots of the Victorian IT dashboard, from 2022-23 Q2 to 2024-25 Q1.
Its planned finish is 28 Jun 2024, 3 months later than the 22 Mar 2024 first planned.
Its latest rating is Green (2024-25 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Unified Communications Infrastructure. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/lmrhaunifiedcommunicationsinfrastructure, as at 18 May 2026. Licence: CC BY 4.0.
Is Unified Communications Infrastructure late? Its planned finish is 28 Jun 2024, 3 months later than the 22 Mar 2024 first planned.
What is Unified Communications Infrastructure's latest rating? Its latest rating is Green (2024-25 Q1).