Case Management System (IBAC) appears in 19 snapshots of the Victorian IT dashboard, from 2017-18 Q2 to 2021-22 Q4.
Its cost is $2.0m at 2021-22 Q4, against $1.3m at its baseline: +53%.
Its planned finish is 30 Jun 2022, 42 months later than the 31 Dec 2018 first planned.
Its latest rating is Green (2021-22 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Case Management System. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/ibaccasemanagementsystem, as at 18 May 2026. Licence: CC BY 4.0.
How much does Case Management System cost? Its cost is $2.0m at 2021-22 Q4, against $1.3m at its baseline: +53%.
Is Case Management System late? Its planned finish is 30 Jun 2022, 42 months later than the 31 Dec 2018 first planned.
What is Case Management System's latest rating? Its latest rating is Green (2021-22 Q4).