Optima Roster System (HRHA) appears in 2 snapshots of the Victorian IT dashboard, from 2025-26 Q1 to 2025-26 Q2.
Its cost is $1.7m at 2025-26 Q2, against $1.1m at its baseline: +53%.
Its planned finish is 28 Nov 2025, 13 months later than the 31 Oct 2024 first planned.
Its latest rating is Green (2025-26 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Optima Roster System. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/hrhaoptimarostersystem, as at 18 May 2026. Licence: CC BY 4.0.
How much does Optima Roster System cost? Its cost is $1.7m at 2025-26 Q2, against $1.1m at its baseline: +53%.
Is Optima Roster System late? Its planned finish is 28 Nov 2025, 13 months later than the 31 Oct 2024 first planned.
What is Optima Roster System's latest rating? Its latest rating is Green (2025-26 Q2).