SDDC and EUC (Holmesglen TAFE) appears in 4 snapshots of the Victorian IT dashboard, from 2017-18 Q2 to 2018-19 Q1.
Its planned finish is 28 Sep 2018, 2 months later than the 31 Jul 2018 first planned.
Its latest rating is Green (2018-19 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: SDDC and EUC. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/holmesglentafesddcandeuc, as at 18 May 2026. Licence: CC BY 4.0.
Is SDDC and EUC late? Its planned finish is 28 Sep 2018, 2 months later than the 31 Jul 2018 first planned.
What is SDDC and EUC's latest rating? Its latest rating is Green (2018-19 Q1).