Systems Readiness (GW Water) appears in 5 snapshots of the Victorian IT dashboard, from 2024-25 Q1 to 2025-26 Q1.
Its cost is $6.1m at 2025-26 Q1, against $4.4m at its baseline: +37%.
Its planned finish is 30 Sep 2025, 3 months later than the 30 Jun 2025 first planned.
Its latest rating is Amber (2025-26 Q1).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Systems Readiness. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/gwwatersystemsreadiness, as at 18 May 2026. Licence: CC BY 4.0.
How much does Systems Readiness cost? Its cost is $6.1m at 2025-26 Q1, against $4.4m at its baseline: +37%.
Is Systems Readiness late? Its planned finish is 30 Sep 2025, 3 months later than the 30 Jun 2025 first planned.
What is Systems Readiness's latest rating? Its latest rating is Amber (2025-26 Q1).