Satellite 1 - Asset (GW Water) appears in 4 snapshots of the Victorian IT dashboard, from 2023-24 Q1 to 2023-24 Q4.
Its cost is $4.3m at 2023-24 Q4, against $3.2m at its baseline: +32%.
Its latest rating is Green (2023-24 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Satellite 1 - Asset. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/gwwatersatellite1asset, as at 18 May 2026. Licence: CC BY 4.0.
How much does Satellite 1 - Asset cost? Its cost is $4.3m at 2023-24 Q4, against $3.2m at its baseline: +32%.
What is Satellite 1 - Asset's latest rating? Its latest rating is Green (2023-24 Q4).