Billing and Collection (GW Water) appears in 12 snapshots of the Victorian IT dashboard, from 2021-22 Q1 to 2023-24 Q4.
Its cost is $99m at 2023-24 Q4, against $40m at its baseline: +147%.
Its planned finish is 30 Jun 2024, 12 months later than the 30 Jun 2023 first planned.
Its latest rating is Green (2023-24 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Billing and Collection. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/gwwaterbillingandcollection, as at 18 May 2026. Licence: CC BY 4.0.
How much does Billing and Collection cost? Its cost is $99m at 2023-24 Q4, against $40m at its baseline: +147%.
Is Billing and Collection late? Its planned finish is 30 Jun 2024, 12 months later than the 30 Jun 2023 first planned.
What is Billing and Collection's latest rating? Its latest rating is Green (2023-24 Q4).