Asset, Works & Field Services Mgmt Consolidation (Concordia) (GW Water) appears in 6 snapshots of the Victorian IT dashboard, from 2024-25 Q1 to 2025-26 Q2.
Its cost is $8.5m at 2025-26 Q2, against $3.4m at its baseline: +147%.
Its planned finish is 30 Jun 2026, 24 months earlier than the 30 Jun 2028 first planned.
Its latest rating is Green (2025-26 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Asset, Works & Field Services Mgmt Consolidation (Concordia). Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/gwwaterassetworksfieldservicesmgmtconsolidationconcordia, as at 18 May 2026. Licence: CC BY 4.0.
How much does Asset, Works & Field Services Mgmt Consolidation (Concordia) cost? Its cost is $8.5m at 2025-26 Q2, against $3.4m at its baseline: +147%.
Is Asset, Works & Field Services Mgmt Consolidation (Concordia) late? Its planned finish is 30 Jun 2026, 24 months earlier than the 30 Jun 2028 first planned.
What is Asset, Works & Field Services Mgmt Consolidation (Concordia)'s latest rating? Its latest rating is Green (2025-26 Q2).