Financial Management Information System (GVR Water) appears in 7 snapshots of the Victorian IT dashboard, from 2017-18 Q2 to 2018-19 Q4.
Its cost is $2.9m at 2018-19 Q4, against $1.4m at its baseline: +107%.
Its planned finish is 28 Feb 2020, 23 months later than the 31 Mar 2018 first planned.
Its latest rating is Amber (2018-19 Q4).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Financial Management Information System. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/gvrwaterfinancialmanagementinformationsystem, as at 18 May 2026. Licence: CC BY 4.0.
How much does Financial Management Information System cost? Its cost is $2.9m at 2018-19 Q4, against $1.4m at its baseline: +107%.
Is Financial Management Information System late? Its planned finish is 28 Feb 2020, 23 months later than the 31 Mar 2018 first planned.
What is Financial Management Information System's latest rating? Its latest rating is Amber (2018-19 Q4).