Asset Management Information System Replacement Project (GVR Water) appears in 27 snapshots of the Victorian IT dashboard, from 2017-18 Q2 to 2023-24 Q4.
Its cost is $4.9m at 2023-24 Q4, against $2.4m at its baseline: +104%.
Its planned finish is 30 Jun 2024, 39 months later than the 31 Mar 2021 first planned.
Its latest rating is Green (2023-24 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Asset Management Information System Replacement Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/gvrwaterassetmanagementinformationsystemreplacementproject, as at 18 May 2026. Licence: CC BY 4.0.
How much does Asset Management Information System Replacement Project cost? Its cost is $4.9m at 2023-24 Q4, against $2.4m at its baseline: +104%.
Is Asset Management Information System Replacement Project late? Its planned finish is 30 Jun 2024, 39 months later than the 31 Mar 2021 first planned.
What is Asset Management Information System Replacement Project's latest rating? Its latest rating is Green (2023-24 Q4).