Server Infrastructure Refresh project (GRHA) appears in 3 snapshots of the Victorian IT dashboard, from 2020-21 Q3 to 2021-22 Q1.
Its cost is $1.8m at 2021-22 Q1, against $1.8m at its baseline: +3%.
Its planned finish is 30 Sep 2021, 2 months later than the 12 Aug 2021 first planned.
Its latest rating is Green (2021-22 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Server Infrastructure Refresh project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/grhaserverinfrastructurerefreshproject, as at 18 May 2026. Licence: CC BY 4.0.
How much does Server Infrastructure Refresh project cost? Its cost is $1.8m at 2021-22 Q1, against $1.8m at its baseline: +3%.
Is Server Infrastructure Refresh project late? Its planned finish is 30 Sep 2021, 2 months later than the 12 Aug 2021 first planned.
What is Server Infrastructure Refresh project's latest rating? Its latest rating is Green (2021-22 Q1).