Geelong Arts Centre Digital Transformation: Implementation of core applications (GPAC) appears in 7 snapshots of the Victorian IT dashboard, from 2022-23 Q2 to 2023-24 Q4.
Its cost is $1.4m at 2023-24 Q4, against $1.2m at its baseline: +16%.
Its planned finish is 30 Jun 2024, 6 months later than the 31 Dec 2023 first planned.
Its latest rating is Green (2023-24 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Geelong Arts Centre Digital Transformation: Implementation of core applications. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/gpacgeelongartscentredigitaltransformationimplementationofcoreapplications, as at 18 May 2026. Licence: CC BY 4.0.
How much does Geelong Arts Centre Digital Transformation: Implementation of core applications cost? Its cost is $1.4m at 2023-24 Q4, against $1.2m at its baseline: +16%.
Is Geelong Arts Centre Digital Transformation: Implementation of core applications late? Its planned finish is 30 Jun 2024, 6 months later than the 31 Dec 2023 first planned.
What is Geelong Arts Centre Digital Transformation: Implementation of core applications's latest rating? Its latest rating is Green (2023-24 Q4).