Primary Data Centre On-Premise Refresh (GMR Water) appears in 8 snapshots of the Victorian IT dashboard, from 2022-23 Q1 to 2023-24 Q4.
Its cost is $1.6m at 2023-24 Q4, against $1.2m at its baseline: +26%.
Its planned finish is 30 Jun 2024, 12 months later than the 30 Jun 2023 first planned.
Its latest rating is Green (2023-24 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Primary Data Centre On-Premise Refresh. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/gmrwaterprimarydatacentreonpremiserefresh, as at 18 May 2026. Licence: CC BY 4.0.
How much does Primary Data Centre On-Premise Refresh cost? Its cost is $1.6m at 2023-24 Q4, against $1.2m at its baseline: +26%.
Is Primary Data Centre On-Premise Refresh late? Its planned finish is 30 Jun 2024, 12 months later than the 30 Jun 2023 first planned.
What is Primary Data Centre On-Premise Refresh's latest rating? Its latest rating is Green (2023-24 Q4).