Response Monitoring and Move-Up Monitoring (FRV) appears in 14 snapshots of the Victorian IT dashboard, from 2021-22 Q2 to 2024-25 Q3.
Its planned finish is 27 Mar 2025, 21 months later than the 30 Jun 2023 first planned.
Its latest rating is Red (2024-25 Q3), down from Amber at 2021-22 Q2.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Response Monitoring and Move-Up Monitoring. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/frvresponsemonitoringandmoveupmonitoring, as at 18 May 2026. Licence: CC BY 4.0.
Is Response Monitoring and Move-Up Monitoring late? Its planned finish is 27 Mar 2025, 21 months later than the 30 Jun 2023 first planned.
What is Response Monitoring and Move-Up Monitoring's latest rating? Its latest rating is Red (2024-25 Q3), down from Amber at 2021-22 Q2.