FRV Operational Station Connectivity (FRV) appears in 18 snapshots of the Victorian IT dashboard, from 2021-22 Q1 to 2025-26 Q2.
Its cost is $18m at 2025-26 Q2, against $17m at its baseline: +10%.
Its planned finish is 17 Aug 2026, 38 months later than the 30 Jun 2023 first planned.
Its latest rating is Green (2025-26 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: FRV Operational Station Connectivity. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/frvfrvoperationalstationconnectivity, as at 18 May 2026. Licence: CC BY 4.0.