Q05283 - Laptop Refresh 2016 (MW) appears in 2 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2015-16 Q4.
Its cost is $1.3m at 2015-16 Q4, against $1.7m at its baseline: -20%.
Its planned finish is 30 Nov 2015, 3 months earlier than the 29 Feb 2016 first planned.
Its latest rating is Green (2015-16 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Q05283 - Laptop Refresh 2016. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/fdf54281-8964-4b4d-88bd-842d26ea9b86, as at 18 May 2026. Licence: CC BY 4.0.
How much does Q05283 - Laptop Refresh 2016 cost? Its cost is $1.3m at 2015-16 Q4, against $1.7m at its baseline: -20%.
Is Q05283 - Laptop Refresh 2016 late? Its planned finish is 30 Nov 2015, 3 months earlier than the 29 Feb 2016 first planned.
What is Q05283 - Laptop Refresh 2016's latest rating? Its latest rating is Green (2015-16 Q4).