Desktop Computers Refresh (Goulburn MW) appears in 2 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2015-16 Q4.
Its cost is $1.1m at 2015-16 Q4, against $1.3m at its baseline: -14%.
Its planned finish is 30 Jun 2016, unchanged from the 30 Jun 2016 first planned.
Its latest rating is Green (2015-16 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Desktop Computers Refresh. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/f87556dc-0462-40a5-9862-f3479ae59724, as at 18 May 2026. Licence: CC BY 4.0.
How much does Desktop Computers Refresh cost? Its cost is $1.1m at 2015-16 Q4, against $1.3m at its baseline: -14%.
Is Desktop Computers Refresh late? Its planned finish is 30 Jun 2016, unchanged from the 30 Jun 2016 first planned.
What is Desktop Computers Refresh's latest rating? Its latest rating is Green (2015-16 Q4).