ICT Redevelopment Stage 3 Hardware Tender (Eye & Ear) appears in 9 snapshots of the Victorian IT dashboard, from 2017-18 Q2 to 2019-20 Q2.
Its planned finish is 31 Mar 2020, 15 months later than the 31 Dec 2018 first planned.
Its latest rating is Green (2019-20 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: ICT Redevelopment Stage 3 Hardware Tender. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/eyeearictredevelopmentstage3hardwaretender, as at 18 May 2026. Licence: CC BY 4.0.
Is ICT Redevelopment Stage 3 Hardware Tender late? Its planned finish is 31 Mar 2020, 15 months later than the 31 Dec 2018 first planned.
What is ICT Redevelopment Stage 3 Hardware Tender's latest rating? Its latest rating is Green (2019-20 Q2).