Computer Aided Despatch (CAD) Upgrade (ESTA) appears in 14 snapshots of the Victorian IT dashboard, from 2017-18 Q4 to 2021-22 Q1.
Its cost is $17m at 2021-22 Q1, against $2.9m at its baseline: +508%.
Its planned finish is 31 Jul 2021, 24 months later than the 31 Jul 2019 first planned.
Its latest rating is Green (2021-22 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Computer Aided Despatch (CAD) Upgrade. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/estacomputeraideddespatchcadupgrade, as at 18 May 2026. Licence: CC BY 4.0.
How much does Computer Aided Despatch (CAD) Upgrade cost? Its cost is $17m at 2021-22 Q1, against $2.9m at its baseline: +508%.
Is Computer Aided Despatch (CAD) Upgrade late? Its planned finish is 31 Jul 2021, 24 months later than the 31 Jul 2019 first planned.
What is Computer Aided Despatch (CAD) Upgrade's latest rating? Its latest rating is Green (2021-22 Q1).