VEU system development based on Dynamics 365 platform (ESC) appears in 13 snapshots of the Victorian IT dashboard, from 2019-20 Q2 to 2022-23 Q2.
Its cost is $2.6m at 2022-23 Q2, against $2.3m at its baseline: +14%.
Its planned finish is 30 Jun 2022, 20 months later than the 30 Oct 2020 first planned.
Its latest rating is Red (2022-23 Q2), down from Green at 2019-20 Q2.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: VEU system development based on Dynamics 365 platform. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/escveusystemdevelopmentbasedondynamics365platform, as at 18 May 2026. Licence: CC BY 4.0.
How much does VEU system development based on Dynamics 365 platform cost? Its cost is $2.6m at 2022-23 Q2, against $2.3m at its baseline: +14%.
Is VEU system development based on Dynamics 365 platform late? Its planned finish is 30 Jun 2022, 20 months later than the 30 Oct 2020 first planned.
What is VEU system development based on Dynamics 365 platform's latest rating? Its latest rating is Red (2022-23 Q2), down from Green at 2019-20 Q2.