MAJ140 - Finance System Upgrade (EPA) appears in 4 snapshots of the Victorian IT dashboard, from 2024-25 Q2 to 2025-26 Q1.
Its cost is $1.7m at 2025-26 Q1, against $1.6m at its baseline: +6%.
Its planned finish is 30 Aug 2025, 2 months later than the 30 Jun 2025 first planned.
Its latest rating is Green (2025-26 Q1), up from Amber at 2024-25 Q2.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: MAJ140 - Finance System Upgrade. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/epamaj140financesystemupgrade, as at 18 May 2026. Licence: CC BY 4.0.
How much does MAJ140 - Finance System Upgrade cost? Its cost is $1.7m at 2025-26 Q1, against $1.6m at its baseline: +6%.
Is MAJ140 - Finance System Upgrade late? Its planned finish is 30 Aug 2025, 2 months later than the 30 Jun 2025 first planned.
What is MAJ140 - Finance System Upgrade's latest rating? Its latest rating is Green (2025-26 Q1), up from Amber at 2024-25 Q2.