MAJ128 - Website and intranet refresh (EPA) appears in 8 snapshots of the Victorian IT dashboard, from 2023-24 Q1 to 2024-25 Q4.
Its cost is $3.9m at 2024-25 Q4, against $2.7m at its baseline: +47%.
Its planned finish is 30 Jun 2025, 12 months later than the 28 Jun 2024 first planned.
Its latest rating is Green (2024-25 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: MAJ128 - Website and intranet refresh. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/epamaj128websiteandintranetrefresh, as at 18 May 2026. Licence: CC BY 4.0.
How much does MAJ128 - Website and intranet refresh cost? Its cost is $3.9m at 2024-25 Q4, against $2.7m at its baseline: +47%.
Is MAJ128 - Website and intranet refresh late? Its planned finish is 30 Jun 2025, 12 months later than the 28 Jun 2024 first planned.
What is MAJ128 - Website and intranet refresh's latest rating? Its latest rating is Green (2024-25 Q4).