MAJ126 - Tasking and Coordination Digital Solution (Enhanced Incident Command) (EPA) appears in 6 snapshots of the Victorian IT dashboard, from 2023-24 Q2 to 2024-25 Q3.
Its cost is $1.6m at 2024-25 Q3, against $1.5m at its baseline: +4%.
Its planned finish is 31 Mar 2025, 10 months later than the 17 May 2024 first planned.
Its latest rating is Green (2024-25 Q3), up from Amber at 2023-24 Q2.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: MAJ126 - Tasking and Coordination Digital Solution (Enhanced Incident Command). Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/epamaj126taskingandcoordinationdigitalsolutionenhancedincidentcommand, as at 18 May 2026. Licence: CC BY 4.0.
How much does MAJ126 - Tasking and Coordination Digital Solution (Enhanced Incident Command) cost? Its cost is $1.6m at 2024-25 Q3, against $1.5m at its baseline: +4%.
Is MAJ126 - Tasking and Coordination Digital Solution (Enhanced Incident Command) late? Its planned finish is 31 Mar 2025, 10 months later than the 17 May 2024 first planned.
What is MAJ126 - Tasking and Coordination Digital Solution (Enhanced Incident Command)'s latest rating? Its latest rating is Green (2024-25 Q3), up from Amber at 2023-24 Q2.