Eastern Health - PCMS Project (EH) appears in 17 snapshots of the Victorian IT dashboard, from 2016-17 Q4 to 2020-21 Q4.
Its cost is $19m at 2020-21 Q4, against $12m at its baseline: +55%.
Its planned finish is 30 Jun 2021, 30 months later than the 31 Dec 2018 first planned.
Its latest rating is Green (2020-21 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Eastern Health - PCMS Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/eheasternhealthpcmsproject, as at 18 May 2026. Licence: CC BY 4.0.
How much does Eastern Health - PCMS Project cost? Its cost is $19m at 2020-21 Q4, against $12m at its baseline: +55%.
Is Eastern Health - PCMS Project late? Its planned finish is 30 Jun 2021, 30 months later than the 31 Dec 2018 first planned.
What is Eastern Health - PCMS Project's latest rating? Its latest rating is Green (2020-21 Q4).